Client | Marian Engineering College, Meenamkulam |
Project Name | Marian Engineering College - Girls' Hostel |
Area in sq. ft. | 26,450 |
Date of handover | 31 Dec 2011 |
The site is adjacent to the Old Ladies’ hostel. Since the sand here was loose and sandy, we had to build an embankment to support the building. This embankment was built using iron sections and sheets – which led to cost overruns. Eventually overcoming all these operational difficulties the building was handed over on time. It took 12 months to complete the entire project.